Heat pump installation: what happens, from survey to switch-on

What happens when an air source heat pump replaces a gas boiler: the survey and written design, the grant paperwork, a cylinder in place of a combi, where the outdoor unit can stand, the electrics, sign-off and what you should be handed at the end.

An air source heat pump installation that replaces a gas boiler runs in three stages: a room-by-room heat-loss survey with a written design, the work on site, and commissioning with a handover of the paperwork. The order matters: in England and Wales, if your home qualifies, your installer applies for the £7,500 Boiler Upgrade Scheme grant, and the voucher should be issued before work starts and then redeemed within three months. A combi home also gains a hot-water cylinder, and the outdoor unit needs a level base with clear space around it.

At a glance

  • Grant. In England and Wales the installer applies for the £7,500 Boiler Upgrade Scheme grant if your home qualifies, and the gas boiler has to go, not stay as a backup. In Scotland you wait for Home Energy Scotland's written offer before any work.
  • Combi homes. You need room for a hot-water cylinder, which stands upright in a frost-free cupboard.
  • Outdoor unit. A level base, a drain or soakaway for condensate and, for propane (R290) units, a protective zone free of drains and openings.
  • Sign-off. Any building-control notification before handover, the electricity network told, an MCS certificate and the controls explained to you.

What changes when a heat pump replaces a gas boiler

A heat pump moves heat from the outside air into your heating water, so the job spreads across the house and garden:

  • The heat source. The boiler and its flue come out. An outdoor unit goes outside, and an indoor unit or controls go inside, often where the boiler was.
  • Hot water. A combi heats water as you use it; a heat pump heats a stored cylinder, so a combi home needs room for one.
  • Radiators. The survey shows whether the existing pipes and radiators can stay; some radiators may need to be larger, because a heat pump is more efficient at lower water temperatures.
  • Electrics. The heat pump gets its own circuit from the consumer unit.

For the Boiler Upgrade Scheme in England and Wales, Ofgem's guidance says an existing fossil-fuel heating system has to be fully replaced; you can't keep one alongside the heat pump as a backup, and a hybrid of heat pump and boiler gets no grant. The rule is about heating, so if you want to keep a gas hob, say so at the survey. The grant comes off your quote and invoice; you never receive the money yourself. Who may qualify is in heat pump grants.

Two cutaway rooms side by side: on the left a wall-hung gas boiler with its flue through the ceiling and a gas meter, on the right a tall indoor unit with a built-in cylinder, controls on the wall and an outdoor heat pump unit on feet outside
Before and after in a combi home: the flue and gas meter go; the cylinder and indoor unit need room inside, the outdoor unit a firm spot outside.

The heat pump installation process, from survey to handover

This is the order in England and Wales, with the Scottish difference at step 4:

  1. Your records. A year of gas bills, your Energy Performance Certificate if you have one, and any rooms that are hard to heat.
  2. Survey and quotes. Each installer surveys the house room by room and gives an itemised quote.
  3. Design and contract. You get the design in writing, and the quote you accept shows the price before the grant, the grant and what you pay after it.
  4. Grant. In England and Wales the installer applies to Ofgem, which then emails you; you have 14 days to confirm consent. In Scotland you apply to Home Energy Scotland and start nothing until its written offer arrives.
  5. Electricity network. The installer notifies your distribution network operator, asking permission in advance where needed.
  6. Installation. The boiler comes out and the heat pump, cylinder and electrics go in, as in the ten steps below.
  7. Gas supply. If nothing else uses gas, ask your supplier to remove the meter once the heat pump is running.
  8. Handover and grant. You receive the certificates and commissioning record; the installer redeems the voucher and you pay the balance.

Step 4 sets the clock. A Boiler Upgrade Scheme voucher for an air source heat pump has to be redeemed within three months, with the work done and commissioned; if the job slips, the installer may have to reapply. A Home Energy Scotland offer gives you up to nine months to do the work and claim. How to compare installers and quotes is in choosing an MCS installer.

The heat-loss survey and the design in writing

Under the MCS design standard MIS 3005-D, the installer calculates each room's heat loss to BS EN 12831-1 and picks a heat pump that covers all of it without the back-up electric heater. Before installation starts, MCS requires the installer to give you in writing:

  • the heat loss of every room, in watts per square metre;
  • the type and size of each radiator or other emitter;
  • the specification of any new hot-water cylinder;
  • the design flow temperature, the temperature of the water leaving the heat pump;
  • the system's seasonal efficiency (SCOP) at that flow temperature.

The flow temperature decides whether your radiators stay. In England, when a whole wet heating system is replaced, including the heat source, radiators and pipework, Building Regulations guidance says it should heat the home at a flow temperature of 55 °C or lower. Rooms whose radiators are too small at that temperature get larger ones.

What the engineers do on site, in ten steps

The drawings follow a house that already has a boiler and a cylinder. In a combi home only the boiler comes out, and the new cylinder needs its own space.

Installation in 10 steps

Step 1 of 10
  1. Cut-away of a two-storey house with radiators; the old boiler and its cylinder stand in the utility room, and a radiator is being measured

    Home survey

    The installer measures the rooms, radiators and consumer unit for the heat loss calculation while the old boiler is still running.

  2. The same house: the boiler and cylinder are only faintly shown, and an arrow shows them being taken away

    Old boiler out

    The old boiler and its hot water cylinder are disconnected and taken away.

  3. Beside the house, two strip footings on gravel with a soakaway pit below; the utility room is empty

    Base

    A firm base for the outdoor unit goes in beside the house.

  4. The outdoor unit stands on its base beside the house

    Outdoor unit

    The unit is set on its base.

  5. A core drill in the utility room; red and blue pipes run from the outdoor unit through the wall

    Through the wall

    A core hole through the outside wall carries the pipes and the cable to the outdoor unit.

  6. The indoor unit and hot water cylinder stand in the utility room, connected to the pipes from the outdoor unit

    Indoor units

    The indoor unit and the hot water cylinder go where the old boiler was.

  7. Red and blue pipes connect the indoor unit, the cylinder and the house’s radiator pipes

    Pipework

    The indoor unit is connected to the existing radiator pipes, and the cylinder to the cold and hot water.

  8. An extended consumer unit with extra devices; cables run to the indoor unit and to the outdoor unit

    Electrics

    The heat pump gets its own circuit at the consumer unit, and the indoor and outdoor units are wired in.

  9. A filling unit with hoses at the cylinder, and valves on the radiators

    Filling and balancing

    The system is filled and bled, and the radiators are balanced at their valves.

  10. The finished system running: heat rises from the radiators, and air flows into the outdoor unit

    Commissioning

    The weather compensation is set, the heat pump is running and the radiators and hot water warm up.

A simplified view of an example home. Your installer decides which steps your home needs after the survey.

From combi boiler to hot-water cylinder

A heat pump heats a stored cylinder, often an unvented one fed at mains pressure, so check the space first. One 210-litre model stands about 1.5 m tall and needs an indoor, frost-free cupboard on a base that takes about 240 kg when full.

Fitting an unvented cylinder is notifiable building work in England and Wales: the installer either tells building control before starting or self-certifies through a competent person scheme for unvented systems, and you receive a certificate. The Legionella cycle, the safety devices and sizing are in heat pump hot water cylinders.

If you already have a boiler with a cylinder, MCS lets the installer reuse it only if its insulation is brought up to the level for a new installation, it is sound, and its size meets the heat pump maker's requirement.

Where the outdoor unit goes

MCS's installation standard, the Building Regulations guidance for England and makers' manuals set out the basics:

WhatWhat to look for
AirflowCold air blown out must not be drawn back in.
BedroomsAway from bedrooms, and not on a wall or floor that carries vibration into the house; use the anti-vibration mounts the maker specifies.
BaseLevel, able to take the weight and vibration, clear of hollows.
SnowNot where snow can bury it; raised or hooded in snowy areas.
CondensateDrained safely to a suitable drain or soakaway.
Cross-section under an outdoor unit: the unit stands on anti-vibration feet on two concrete strips, with a gravel-filled pit and a drain pipe below for the condensate
One way to build a ground base: anti-vibration feet on two concrete strips, with the condensate draining into a gravel pit.

Condensate forms on the outdoor coil, including when the unit defrosts itself in cold weather, and has to drain away rather than freeze on a path.

Drawing of an outdoor unit on two concrete strips, with a pit filled with gravel below it and water dripping from the unit into the pit
Condensate drips into a pit of coarse gravel and soaks away instead of icing over.
PositionFixingCondensateWatch for
On the groundstand or feet on two concrete stripsinto a gravel pit or draina level base and free airflow
On the wallwall bracketsto a gravel strip or drain belowthe wall must carry the unit; keep vibration away from bedrooms
Insidea model made for it, with air ducts through the wallas the maker's manual sayssound attenuation on internal fans and ducts
Three house walls side by side: an outdoor unit on two concrete plinths over gravel, an outdoor unit on wall brackets above a gravel strip, and a cut-away room with a unit indoors drawing and blowing air through two ducts in the outside wall
On the ground, on wall brackets or indoors with air ducts through the wall; an indoor position needs a model made for it.

Some units, such as Mitsubishi Electric's Ecodan R290 range, use propane (R290) as their refrigerant. Propane is highly flammable and heavier than air, so the maker sets a protective zone. For an Ecodan R290 unit in front of a wall, it is a low zone, 0.3 m deep above the ground, that reaches 1 m to each side and in front of the unit and back to the wall; at a corner it stretches 2.5 m in front. The zone must hold no doors, windows, vents, gullies, downpipes, sockets, lamps or switches, and must not cross the property boundary, a footpath or a driveway. Other models set their own zones.

Outdoor unit on the ground in front of a house wall, with a pale blue zone marked on the ground around it; a low-level window well sits inside the zone to the left
The marked zone around a propane unit must stay clear. With a low-level window well inside it, the unit couldn't stand here.

How distance and nearby walls change what your neighbours hear is in how loud is a heat pump. In England and Wales a unit on a house is usually permitted development if it passes the MCS 020(a) noise calculation of 37 dB(A) at a neighbour's window or door and meets the size and siting conditions; listed buildings are outside permitted development. Check with your local planning authority, and see heat pump planning permission.

Worked example: placing the unit at our example home

Our example home is a 1970s semi-detached house in England, 97 m², with radiators and a gas combi boiler. The garden layout is our own illustration: on the back wall, the kitchen downpipe's gully 0.7 m to one side of the planned spot and the boundary fence 1.2 m to the other; at the side, a passage 2.5 m wide to the next boundary. The unit is Mitsubishi Electric's 8 kW Ecodan R290, 1,050 × 480 × 1,020 mm and 117 kg, in front of a wall; other models differ.

CheckBack wallSide wall
Wall the zone needs1.0 + 1.05 + 1.0 = 3.05 m3.05 m
Wall free1.2 + 1.05 + 0.7 = 2.95 mover 3.05 m, no door, vent or gully
Boundary1.2 m, outside the zone2.5 − 0.48 − 1.0 = 1.02 m left for the gap behind the unit
Unit volume (England limit 1.5 m³)1.05 × 0.48 × 1.02 = 0.51 m³0.51 m³
Result0.10 m short: doesn't fitfits if the manual's rear gap is under 1.02 m

At the back, moving the unit away from the gully only pushes its zone over the fence. At the side, the zone stays on your land and the base has to carry 117 kg; the installer still runs the MCS 020(a) noise calculation and checks that no bedroom sits behind that wall.

Electrics and the electricity network

MCS requires the installer to check that your electricity supply is adequate for the heat pump and to notify the distribution network operator under the Energy Networks Association's procedures, asking permission before installation where needed. The example unit runs on a single-phase supply, and its datasheet lists a 25 A circuit breaker as guidance; a qualified electrician chooses the cable and breaker. Expect a new circuit, cabling to both units and possibly a new consumer unit: ask for it all to be priced, and who certifies it.

A grey weatherproof isolator switch box with a round rotary handle and a cable gland underneath
An isolator switch beside the outdoor unit lets an engineer cut its power on the spot; check whether your quote includes one.

Sign-off, commissioning and handover

Building Regulations. In England and Wales, installing or replacing a heating system may need building regulations approval. You don't need to arrange it yourself if the installer is registered with a competent person scheme for the work; keep the certificates of compliance, as you may need them when you sell. MCS requires the installer to say who handles any notification and to complete it before handover. Scotland has its own system under the Building (Scotland) Act 2003, where some work needs a building warrant, and Northern Ireland has the Building Regulations (Northern Ireland) 2012; ask your installer which applies.

Commissioning. The installer fills and balances the system and sets up the controls. MCS asks for weather compensation, which moves the flow temperature with the weather outside, wherever it helps efficiency, and its commissioning record asks whether the controls were explained to you: ask for that walk-through.

Handover. Ofgem's guidance says the installer should give you post-installation documents, which may include an MCS certificate. Ask for the design, the commissioning record and any building regulations certificate too.

The gas meter. In Great Britain, when a gas meter is removed and not replaced, the supplier that last supplied gas through it must seal off the supply. If no meter returns within 12 months and there is no separate service valve, the service pipe has to be disconnected as near the main as reasonably practicable. Ask your supplier about any charge and when the standing charge stops.

Two views of the same house: on the left the gas service pipe runs underground into the house and ends in a capped, tagged stub on the wall below a wall cupboard; on the right the pipe has been dug out through an open trench, leaving a sealed hole in the wall
Ending a gas supply: first the supply is sealed off (left); after 12 months without a meter, where there is no separate service valve, the pipe is disconnected near the main and any length left in the ground is sealed.

What the whole job costs is in heat pump cost: the median air source heat pump installed under the Boiler Upgrade Scheme in England and Wales cost £12,826 in July to September 2026, as reported by MCS installers, before the grant.

Checklist: before work starts

Before you agree a start date

  • A written programme: your start date, the days on site, and when your heating and hot water will be off.
  • Where the outdoor unit, indoor unit and cylinder will go, marked on a plan or on site.
  • The outdoor unit's protective zone checked against doors, gullies, vents and the boundary.
  • Who notifies building control or the network operator, and which certificates you will get.
  • In England and Wales, the voucher issued; in Scotland, Home Energy Scotland's written offer received.
  • What happens to the old boiler, its flue opening and the gas supply.

Figures that change

WhatValueApplies
Boiler Upgrade Scheme grant£7,500 for an air-to-water or ground source heat pumpEngland and Wales, if the home qualifies
Voucher validityredeemed within 3 months for an air source heat pumpEngland and Wales, Ofgem guidance V5.1
Home Energy Scotlandgrant up to £7,500 for a heat pump, plus a £1,500 uplift for rural and island homes; nine months to install and claimScotland
Air source heat pump, installedmedian £12,826July–September 2026, Boiler Upgrade Scheme installations in England and Wales, reported by MCS installers, before the grant

How we worked this out

The placement example uses our example home (a 1970s gas semi in England, 97 m²), a garden layout we made up and one manufacturer's published dimensions and protective zone; other models differ. It isn't a design or a planning assessment. More in our editorial method.

Frequently asked questions

How long does heat pump installation take?

There is no official figure for days on site, so ask the installer for a programme with the quote. The paperwork sets the outer limits: in England and Wales a Boiler Upgrade Scheme voucher for an air source heat pump must be redeemed within three months, and in Scotland a Home Energy Scotland offer gives you up to nine months to finish and claim.

Can a heat pump be installed indoors?

The indoor unit, controls and cylinder go inside, but the part that collects heat needs outside air. A unit standing indoors would need a model made for it, with air ducts through the wall, and MCS's installation standard asks for sound attenuation on internal fans and ducts where needed. Ask the installer whether the model offered can go inside.

Can I install a heat pump myself?

Not if you want a grant. The Boiler Upgrade Scheme in England and Wales is installer-led, you can't apply yourself, and every installation must be carried out by an MCS-certified installer; Home Energy Scotland also requires an MCS-certified installer and product. Parts of the job need qualified people anyway: in Great Britain only someone competent may work on a gas fitting such as your boiler, the example unit's datasheet leaves the cable and breaker to a qualified electrician, and an unvented cylinder is notifiable building work in England and Wales unless a registered installer self-certifies.

Will I need new radiators?

Often only some. The survey shows each room's heat loss and the radiators needed at the design flow temperature; in England a fully replaced system should be designed for 55 °C or lower, so rooms with small radiators are where larger ones go in.

What happens to my gas meter?

Ask your supplier to remove it once the heat pump is running, if nothing else in the house uses gas. The supply is then sealed off; if no meter goes back within 12 months and there is no separate service valve, the service pipe is disconnected near the main.